|
||
WestCon TribuneFebruary 2004 |
||
|
January Review
Spanning the Carquinez Strait Building the Alfred Zampa Memorial Bridge Presented
By: Bart Ney, Public
Information Manager, Caltrans Project Manager, Moore, Iacofano,Goltsman
Inc.
The new year started
out with an outstanding presentation by Bart Ney, Public Information
Manager for Caltrans and a project manager for Moore, Iacofano,
Goltsman. Assisted by a video which will be used in an upcoming
documentary, Mr. Ney conveyed a visual overview of the building
of the Alfred Zampa Memorial Bridge, more commonly known as the
Carquinez Bridge. In 1988 a mandate passed
by voters increased bridge tolls from sixty cents to a dollar. The
increase in tolls paid for all of the work done to build the bridge
at a cost of $200 million. The site already had
two bridges on it, one built in 1927 and the second built in 1958.
These two spans carried on average 109,000 drivers each day. Both
of the current structures did not meet seismic design or traffic
safety standards. The 1958 bridge was able to be retrofitted, but
the 1927 span exhibited deterioration to the metal components and
could not be kept in use during retrofitting, and therefore replacement
was a better option. One main reason for
building a suspension bridge was that the load is being held by
the main cables and only two towers. Not having to build a tower
in the middle of the strait saved money, maintenance problems and
safety issues involving workers. The new bridge is the first suspension in the
country that has concrete towers and pile foundations. The steel
casings are ten feet in diameter and 150 feet long. The piles go
down into the ground at least 300 feet so they are as deep underwater
as the old bridges are tall. There are six pilings for each tower
leg. The towers are about
400 feet tall and contain about 3000 metric tons of concrete each.
The west tower shaft contains an elevator and the east side houses
a stair case. Cable spinners were
used to put in the 13,000 miles of cables in place. Cable spinning
is not a new technique, but
modern use of computers allowed tension to be calculated
and consistent and eliminated the need for additional wire workers
to control placement and tension. Each strand of wire is about 5
millimeters and strong enough to hold up a Hummer vehicle. There
are 8,584 strands of wire in each cable and each cable is one continuous
strand of wire. After cables were spun a compacting machine was
used to compress the cables into a cylinder and cable bands were
applied. The cross structure
that is driven on is hollow and is supported by 90 degree angles.
There were 24 sections needed for the bridge, each weighing about
600 tons which is actually lighter than regular construction. The
hollow plates allow for a crawl space that is used for utility lines,
protecting them from the sea air and assist in easier maintenance. To place
these sections, a new
method was invented. The process actually allowed the panels to
be lifted from a barge underneath and climb themselves into place
by strand jacks where they were locked in permanently by workers.
Due to obstruction, a few of the panels had to be placed on diagonal
strand jacks and swung into place. Learning from the 1989
earthquake and the problems with the Bay Bridge, this span has no
regular expansion joints. All 24 segments were welded together to
create one continuous piece. There are steel locker arms which allow
movement. Four feet of movement is accommodated on either side of
the bridge for earthquakes and normal heat expansion and contraction. Alfred Zampa was an
ironworker who lived in Crockett and worked on all of the bridges
built in the Bay Area. He actually is one of the very few workers
to survive a fall from the Golden Gate Bridge. After being released
from the hospital, he returned to the top of the tower to continue
his job. In 2000 when the project started on the bridge, Mr. Zampa
assisted with the ground breaking ceremonies. He died shortly after
the start of construction. Mr. Zampa is the first “blue collar
worker” to have a bridge named after him. Our thanks to Mr. Ney
for an informative, educational and entertaining presentation. If you missed this, you may want to keep
an eye out for the documentary which will be shown soon on television.
|
||
|
MEETINGS, BULLETIN BOARD, MENU, PAST ISSUES Published monthly by WESTCON (Westcon Consultants Association)
for general membership and friends. Publication of original articles or
reprinted material does not imply approval or endorsement. Submitted material
becomes property of WESTCON. Not responsible for accuracy of content.
Views and opinions expressed are not necessarily those of editors of WESTCON.
|
||